Mitete Town Council has today, 6th August 2024, officially handed over contracts worth K6.9m to ten (10) local contractors under the Community Projects Component of the 2024 Lukulu West Constituency Development Fund (CDF) allocation.

The project to be undertaken includes:

  1. Completion of a 1×2 Classroom Block at Washishi Primary School in Kakawacha Ward.

Contractor/Supplier: Topply Logistics

Duration of the Contract: Two (2) months

  1. Construction of a 1×3 Classroom Block at Chipepepe Primary School in Lutembwe Ward.

Contractor/ supplier: Luhume General Dealers

Duration of the Contract: Six (6) months

3.Completion of a 1×3 Classroom Block at Mbumi Primary School in Lwambimba Ward.

Duration of the Contract: three (3) months

  1. Completion of a 1x3x2 Classroom Block at Nangoma Primary School in Lutembwe

Contractor/ Supplier: Muzakamizhi Genral Dealers

Duration of the Contract: Four (4) months

  1. Construction of a Staff House at Lwee Health Post in Muyondoti

Contactor/ Supplier: Brian Koota Enterprise

Duration of the Contract: Three (3) months

  1. Construction of a Maternity Annex at Kashizhi Health Post in Kashizhi Ward

Contractor/ Supplier: MC Kangunge Enterprise

Duration of the Contract: Three (3) months

  1. Construction of a staff House at Kashizhi Health Post in Kashizhi Ward

Contractor/ Supplier: Kamubamwi Enterprise

Duration of the Contract: Six (6) months

  1. Drilling and installation of 02 Solar Powered Boreholes at Nyala and Lwee Muyondoti

Contractor/ Supplier: GNKAN Engineering and Construction Limited

Duration of the Contract: Two (2) months

  1. Rehabilitation of a 1×3 Classroom Block at Lubelele Primary School in Mataba Ward under the 2024 CDF Disaster Component

Contractor/ Supplier: Kamubamwi Enterprises

Duration of the Contract: Three (3) months

  1. Rehabilitation of a 1×3 Classroom Block at Lute Primary School in Mataba Ward under the 2024 CDF Disaster component.

Contractor/ Supplier: Lyakwa Enterprise

Duration of the Contract: Three (3) months.